Doosan Heavy Industries & Construction completes the construction of Vinh Tan 4 Thermal Power Plant in Vietnam

2019. 09. 22

게시글 내용

- New 1,200MW power plant in Binh Thuan east of Ho Chi Minh City will resolve power shortage in southern Vietnam
- DHIC wins eight projects in Vietnam since 2010

  • □ Doosan Heavy Industries & Construction (DHIC) announced on September 22 that it had held the construction completion ceremony for the Vinh Tan 4 Thermal Power Plant ordered by Electricity of Vietnam (EVN).

  • □ Held in Binh Thuan province on September 21, the ceremony was attended by Vietnamese Deputy PM Truong Hoa Binh, EVN Chairman Duong Quang Thanh and CEO of DHIC Plant EPC BG Inwon Park.

  • □ The Vinh Tan 4 Thermal Power Plant has been built in Binh Thuan province, about 230 km east of Ho Chi Minh City, to resolve the power shortage in southern Vietnam. DHIC received the turn-key project to construct the 1,200 MW (600 MW*2) power plant for about KRW 1.6 trillion in 2013, and has been responsible for the entire EPC process from design and equipment manufacturing to installation and commissioning.

  • □ “Since the construction of the Mong Duong II Coal-Fired Power Plant in 2010, DHIC has been recognized for its know-how in Vietnam, receiving eight projects in total. We plan to broaden our presence in the Vietnamese power generation market, which is expected to expand its power generation capacity to 136 GW by 2030,” said Inwon Park, CEO of the DHIC Plant EPC BG. <End>

The construction completion ceremony for the Vinh Tan 4 Thermal Power Plant ordered by EVN was held in Binh Thuan province, Vietnam. Key officials including CEO of DHIC Plant EPC BG Inwon Park (first from the right) and Vietnamese Deputy PM Truong Hoa Binh (sixth from the right) attended the ceremony.